Welcome to the official construction update page for Curtice Village. This page provides ongoing updates for residents regarding construction progress, timelines, and important notices related to our community improvement project.
We are committed to keeping all homeowners informed throughout every phase of construction. Please check back regularly for the latest updates, and don't hesitate to reach out with any questions or concerns.

Follow our weekly construction progress below.
Interior framing has started on buildings A and B. Electrical rough-in is scheduled to begin next week. Residents may notice increased truck activity in the mornings.
The city inspector approved the foundation work for all units. Concrete curing is on schedule and structural steel delivery is confirmed for next week.
Foundation pouring has been completed for the main building. Curing process is underway and expected to take 7–10 days. No major delays anticipated.
Construction has officially begun! Site preparation, including grading and temporary fencing installation, was completed this week. Equipment staging is in progress.
Official construction documents and repair specifications prepared by Knott Laboratory, LLC.
Curtice Village — Construction Repair Plans
Full scope of repairs including structural, waterproofing, siding, phase schedule, and materials specifications.